Please note below the list of renovation projects that will be ongoing throughout the month of February. Project notifications will be posted in common areas relative to the project locations in order to provide further details on the scope of work, affected areas and duration of the scheduled work. Please be aware of the work at hand and observe any signage redirecting pedestrian traffic away from potential health and safety hazards. All work has been scheduled as much as possible to avoid interruption with ongoing classes, however if there are any concerns please do not hesitate to contact Facilities Services.
Location Brief Description of Work
TRAFALGAR CAMPUS
A-Wing 2nd Floor Hallway: Installation of floor tile underneath lockers.
AA-Wing Miscellaneous Areas: Upgrades to existing HVAC.
AA1d/AA1e: Installation of new lighting and controls.
B-Wing 1st Floor Hallway: Painting walls & installation of display cabinets.
B103b/B106d: Painting.
B122: Modifications to closet storage area.
C210 Lab: Installation of observation room door.
C241/C215 Labs: Installation of light fixtures.
E-Wing 1st & 2nd Floor Hallways: Relocation of existing data cabling, installation of new lights and ceiling tile.
E202 Faculty Office: Renovation for new office space.
G-Wing all Floor Hallways: Installation of wall base trim.
J-Wing Stairs: Installation of granite edge trim.
J-Wing Hallways: Installation of wall base trim.
J114 Meeting Room: Modification of existing sliding door.
Residence Conference Room: Modifications for IAPS.
DAVIS CAMPUS
B127 Classroom: Flooring replacement.
Student Centre Office: Office renovation.
Chemistry Wing Mechanical Room: Pump relocation & piping rework.
J-Wing Learning Commons Painting & wall repairs.