Please note below a list of renovation projects that will be ongoing throughout the month of June. Project notifications will be posted in common areas relative to the project locations in order to provide further details on the scope of work, affected areas and duration of the scheduled work. Please be aware of the work at hand and observe any signage redirecting pedestrian traffic away from potential health and safety hazards. All work has been scheduled as much as possible to avoid interruption with ongoing classes, however if there are any concerns please do not hesitate to contact Facilities Services.
Location | Brief Description of Work |
TRAFALGAR CAMPUS | |
Athletics Building | Mechanical upgrades effecting HVAC, chilled water & heating |
A-wing & Athletics Building | New electrical service and water main replacement |
A-wing | A117 & A143 classroom renovations |
Annie Smith | AA1b classroom renovation |
B-wing Basement | Office upgrades |
B-wing & J-wing | Miscellaneous washroom upgrades |
B-wing | B122d office renovation |
B-wing | B115b sound booth installation (affect B115a) |
B-wing | New One Card office / Grassroots |
B-wing | BB10 Studio renovation |
B-wing | B244 office reconfiguration |
C-wing | C105 Library office renovation |
C-wing | C224 & C225 classroom renovation |
C-wing | HVAC, building automation upgrades & corridor lighting |
G-wing | HVAC, building automation upgrades & corridor lighting |
G-wing | Building closure & shut down from June 20st to July 7th |
J-wing | J218 classroom renovation (affect J216) |
S-wing | S318 & S318a classroom/office/storage renovation |
S-wing | S403 office renovation |
South side of campus-Exterior | Cabling along trails |
Campus wide | Chilled water renovations (limited access in tunnels) |
Campus wide | Heat exchanger renovations |
Location | Brief Description of Work |
DAVIS CAMPUS | |
B-wing (chemistry wing) | Pump relocation & piping rework |
B-wing (Hollend room) | Faculty office renovation |
B-wing | Elevator refurbishment (additional information will be posted) |
B-wing | B104 office reconfiguration |
B-wing | B219 office reconfiguration |
C-wing | C123 & C131 interior refurbishing |
C-wing | HVAC, building automation upgrades & corridor lighting |
Campus wide | Chilled water renovations |