Sheridan College Facilities Projects is upgrading the current roof in a section of B-wing and A-wing. Starting July 25th, 2013, this work will be taking place. Your co-operation and patience during this project is appreciated.
Construction Details
The roof is being replaced over part of the B-wing area affecting B117/B118 offices and classrooms B115, B115a, B115b, B115c, B115d. We will also be replacing the failing skylights in the B117/B118 area. During this removal, we may ask that no one be inside the office space during the removal/replacement for safety reasons.
We will also be doing a partial roof replacement on the high A-wing roof, over the east side. This area affects parts of Grenville, the mailroom, A125, A126 and A127 areas. This part of the project won’t commence until the B-wing roof is completed.
The replacement of the roof will take approximately two weeks and we will be trying to conduct early morning starts to minimize the noise inside. Work will typically take place between 6:00am and 5:00pm, Monday to Friday, with work after hours and on weekends only as required.
Most work will take place outside, however the trades may enter the areas to inspect the roof drains during/after the replacement process.
All work is weather dependent.
Disruptions
As with all construction projects, there will be noise and temporary inconveniences at times. There will be smells from the roofing materials when the new roof is being installed. In order to complete the work effectively, some pedestrian restrictions will be necessary. During the project, the area in front of Door B17 will be closed off for safety reasons.
Sheridan College Facilities Projects looks forward to working with you to allow our Contractor to complete this project in a professional and timely manner. Every effort will be made to reduce any inconvenience you may encounter.
For more information, contact:
Building Services and Maintenance
Ph. 905-845-9430 Ext. 2255