Trafalgar data centre transfer switch replacement – timelines and service impacts

$
0
0

As indicated in the email sent to all Sheridan staff on September 15, during the upcoming Thanksgiving Weekend (October 10-13), Facilities Management will be replacing the electrical transfer switch that feeds power to the Trafalgar campus data centre. This will require a complete shutdown of the equipment in the data centre while the electrical work is being performed. Consequently, many IT services will be unavailable during the upgrade period. Below is a rundown of the timelines associated with this work.

Friday, October 10 starting at 6 pm:

  • IT begins shutting down services hosted in the Trafalgar data centre

Friday overnight into Saturday morning:

  • Facilities Management and their contractor replace the electrical equipment

Saturday, October 11 – afternoon into the night:

  • IT will start bringing up the data centre network, storage, server, and virtualization infrastructure

Sunday, October 12:

  • IT will be bringing up applications and services

Monday, October 13:

  • Testing and remediation of any discovered issues

For complete details of the services affected, please visit our Service Impact page at: http://it.sheridancollege.ca/news/transfer-switch-service-impact.html

If you have any questions or concerns, send email to helpdesk@sheridancollege.ca.